Solar Plant Cost & ROI

5 MW solar power plant cost in Gujarat

A complete, independent cost, land, generation and return breakdown for a 5 MW ground-mount solar plant in Gujarat.

Open ROI calculator
₹19 Cr
Approx. project cost
15–20
Acres of land
83.2L
Units / year
6.4–9.7 yr
Payback
Who a 5 MW plant is for

A 5 MW plant is the maximum size under the DREBP scheme — the single most popular utility-scale ticket for serious ₹5–25 crore investors.

The flagship DREBP size, with a fixed 25-year PPA.

5 MW at a glance

₹19 Cr
Total project cost
15–20 acres
Land required
83.2L
Units / year
6.4–9.7 yrs
Payback

The economics of a 5 MW plant, in plain words

Over its 25-year life a 5 MW plant in Gujarat generates about 83.2 lakh units a year. Under a DREBP PPA at ₹2.76/unit that is roughly ₹2.3 crore of revenue a year; on open access nearer ₹3.33 crore. After ₹0.35 crore of annual O&M, net income runs ₹1.95–2.98 crore a year, so the ₹19 crore build pays back in about 6.4–9.7 years and then earns largely profit. Claiming 40% accelerated depreciation shields roughly ₹1.9 crore of tax in year one, and undiscounted 25-year PPA revenue is around ₹57.5 crore.

5 MW cost & return breakdown

Sourced figures — not an EPC quote.

Parameter5 MWvalue (indicative)
Total project cost (CAPEX)₹19 Cr
Land required15–20 acres
Annual generation83.2 lakh units/yr
Annual revenue (DREBP PPA)₹2.3 Cr/yr
Annual revenue (open access)₹3.33 Cr/yr
Annual O&M cost₹0.35 Cr/yr
Net annual income₹1.95 – 2.98 Cr/yr
Payback period6.4 – 9.7 yrs
Year-1 AD tax benefit (40%)₹1.9 Cr
25-year gross revenue (PPA)₹57.5 Cr

Assumptions: 19% CUF, ground-mount EPC cost, Gujarat irradiance. Actual figures vary by site.

Key considerations for a DREBP-scale plant

At 5 MW you are at the DREBP sweet spot — up to the 5 MW scheme ceiling, on a fixed 25-year PPA with the discom at a known tariff. It needs about 15–20 acres near a single 66 kV substation with evacuation headroom. The whole return hinges on that land-to-substation fit, so site selection and the DREBP registration matter more than shaving the EPC price.

~15–20 acres by a 66 kV substation
DREBP fixed 25-year PPA (≤5 MW)
Substation headroom decides feasibility
Clean title + DREBP registration first

An estimate isn’t a quote.

For your 5 MW project, we tender it across our EPC network and negotiate your best real price — with the hidden costs exposed.

Frequently Asked Questions

A 5 MW ground-mount solar plant in Gujarat costs roughly ₹19 crore turnkey — modules, inverters, structures, civil works and grid connection. DCR-module projects cost ~₹0.8–1.0 crore/MW more.

Get an exact quote for your 5 MW plant

We tender it across our EPC network and negotiate your best price.